GENERATOR > REASSEMBLY

for Preparation Click here



1. INSTALL GENERATOR ROTOR ASSEMBLY
  1. Install the rotor to the drive end frame.



2. INSTALL GENERATOR PULLEY WITH CLUTCH


    A117286
  1. Install the spacer ring.

  1. Install the pulley by hand.



    B057312E04
  1. Install SST to the pulley and vise as shown in the illustration.

    SST
    09820-63020  

  1. Mount SST (A) in a vise.



    A074018E02
  1. Turn SST (B) counterclockwise to tighten the pulley.

    Torque:
    80 N*m{ 816 kgf*cm , 59 ft.*lbf }

  1. Check that the generator pulley rotates smoothly.



3. INSTALL FITTING RING


    A117274
  1. Align the 3 cutouts of the fitting ring with the stator generator with rectifier.



4. INSTALL GENERATOR STATOR SUB-ASSEMBLY WITH RECTIFIER
  1. Align the key of the drive end frame with the keyway of the generator stator.



    A117272
  1. Install the stator with the 4 screws.

    Torque:
    4.3 N*m{ 44 kgf*cm , 38 in.*lbf }



5. INSTALL VOLTAGE REGULATOR SUB-ASSEMBLY WITH BRUSH


    A121957
  1. Attach the brushes and terminals to the rectifier end frame of the regulator.



  1. Install the regulator with the 3 screws.


    A121958E01

    Torque:
    2.2 N*m{ 22 kgf*cm , 19 in.*lbf } for screw A
    1.2 N*m{ 12 kgf*cm , 11 in.*lbf } for screw B

    HINT:
    Install screw B to the position shown in the illustration.



6. INSTALL GENERATOR REAR END COVER


    A117270E01
  1. Install the rear end cover with the 2 nuts and screw.

    NOTICE:
    The protective tower must be attached on the end cover.

    Torque:
    19 N*m{ 194 kgf*cm , 14 ft.*lbf } for nut A
    12 N*m{ 122 kgf*cm , 9 ft.*lbf } for nut B
    2.4 N*m{ 24 kgf*cm , 21 in.*lbf } for screw



    A117269
  1. Install the 2 terminal covers by turning them clockwise.